Achievement Rates Traineeship Analysis

This report applies only to English contracts.

Certain learning aims are excluded from the traineeship Achievement Rates. The exclusion rules are applied based on the QAR ruleset that you run the report with (this can be chosen in the parameters):

The Achievement Rates Traineeship Analysis report shows Traineeship Achievement Rate figures under a number of groupings. The groupings are highly customisable to allow for in-depth analysis.

Parameters

Layout

The report data has custom row (left) and column (top) groupings which are determined by the parameters. These can be expanded and collapsed by clicking the and buttons.

For each grouping, the data area shows one of four measures:

Each of these includes a 'traffic light' (green, amber or red) which is set according to the values in the threshold parameters. This allows you to quickly see general achievement levels for each area.

Clicking the left or right hand number in any cell will show a list of the relevant aims.

Explanation of Timely and Overall Cohorts

Achievement Rates are measured in overall and timely cohorts, which are defined by the ESFA. A cohort is simply a group of aims during a period of time. The Maytas Achievement Rates reports distinguish between cohort years (based on contract years) and cohort months. For example, an aim with a timely cohort month of August 2021 would have a timely cohort year of 2021/22.

Timely Cohort

An aim's timely cohort is determined by the month/year in which the planned end date falls. For example, if an aim had a planned end date of 01/09/2021, the timely cohort month would be September 2021 and the timely cohort year would be 2021/22.

To be a timely achiever, an aim must be achieved within 90 days of the planned end date (or before the planned end date). This requires a completion status of 2 (completed) and an outcome of 1 (achieved). If an aim is a timely achiever, the timely achiever cohort year and month is the same as the timely cohort.

It is important to note that the 90 day rule only applies when determining timely achievers, not the timely cohort. i.e. If an aim ends more than 90 days after the planned end date, it would not be counted as a timely achiever but it would still be counted in the timely cohort.

The timely cohort can include live aims as well as ended aims.

Overall Cohort

An aim's overall cohort is determined by the month/year in which the latest out of the planned end date and the actual end date falls. In other words, if the planned end date is after the actual end date, the planned end date is used, otherwise the actual end date is used.

It is important to note that the overall cohort only includes aims with an actual end date, unlike the timely cohort.

To be an overall completer, an aim must have a completion status of 2 (completed). To be an overall achiever, an aim must have a completion status of 2 (completed) and an outcome of 1 (achieved). Unlike the timely cohort, it does not matter when the achievement takes place. If an aim is an overall completer or achiever, the overall completer or achiever cohort year and month is the same as the overall cohort.

Forecasting

The Forecast data parameter has three options:

For the best case and worst case scenarios, if the planned end date is in the past then the completion is forecast for the current period. The exception to this is when aims in the timely cohort are still live and more than 90 days past the planned end date, in which case they are forecast to be completed without achievement in the current period.

There are certain situations worth noting when using the forecasting:

Achievement Rates Reconciling vs Anticipated Results

We have received queries and feedback from providers around how the achievement rates data is produced and what that data represents. Since the major QAR rule changes were introduced in January 2017, our intention has been to produce what we expect the latest published QAR results to be. This means that in some cases, data which was exported in recent contract years has been ignored in favour of earlier data, as the earlier data is what we expect the ESFA to be using to produce the latest QARs.

While this is the most accurate way to reconcile against current published figures, it is not useful for showing future expected results based on current data. To address this, the reports allow you to toggle between these two options with the Reconcile or predict parameter: